We were contracted to provide the design, manufacture and installation of the light gauge steel structure for 12 apartments in Edgware Road London. Located on an extremely tight site, with two different types of substructure, one of the key challenges was to manage access and construction whilst keeping disruption to a minimum – a challenge to which pre-assembled framing systems are well suited.

Our solution was a factory assembled, pre-insulated load bearing wall, floor and roof system, consolidating a number of elements into one system. Not only did this address the challenge of the tight site and reduce the number of deliveries necessary, it also accelerated the build programme as all walls and floors were pre-formed in our factory and shipped ready for rapid site installation. We delivered the site on time (keeping to a six week programme), and on budget.